How to install the air feeder

How to install the air feeder

First.the air feeder installation accessories:
1.The installation board, is made of cast iron made of a rectangular plate, one side is a vertical long hole, one side is a shorter cross hole.
air-feeder-accessories
2.The installation of screws. Depending on the model, the mounting screws are not the same.
3.Oil and water separator. To prevent the air compressor through the trachea into the air feeder, so that the machine can not run properly, the other is the oil drum to the air feeder lubrication.
4.High pressure trachea. Connect the air supply to the air feeder and pass the air supply to the air feeder.
air-feeder-assembly
5.Feeding handle. The role is to pass the air feeder feed signal accessories, control the air feeder at a few minutes feeding.
6.Wearing parts. According to different models and configuration.
air-feeder-use
Second.the air feeder installation process:
1.First determine the air feeder to install to the punch where the air feeder can be installed on the left side of the press can also be installed in the punch on the right, this should be based on the customer’s stamping die and the scene to determine.
2.The right angle plate placed in the punch to install the table, the installation plate vertical hole side of the press plate side of the plate, draw a good hole.
3.After playing two screw holes, the right angle plate directly with screws fixed in the punch on the side of the platform.
4.And then the air feeder mainframe part with screws fixed on the right angle plate.
5.According to the installation of the air feeder of the host’s floating lever position to find the location of the installation of the pole. The pole is mounted on the punch plate. In the side of the disk to play two screw holes, the pole will be fixed in the corresponding above the floating pole on it.
6.And finally in the installation of the air feeder under the punch machine body to play two screw holes fixed triple combination filter, air inlet connected to the gas source, and then connected to the high pressure air pipe and air feeder, the entire installation finished.